Gov. Mikie Sherrill joined NJ TRANSIT, Amtrak, and federal officials in Kearny on Monday to celebrate the completion of the Portal North Bridge cutover, officially placing both tracks of the new high-level span into full service and retiring the 116-year-old swing bridge over the Hackensack River.
The milestone marks the first completed project among the 11 components of the broader Gateway Program along the Northeast Corridor—the nation’s busiest rail line. Following the conclusion of a five-week second-track cutover that began Oct. 9, regular NJ TRANSIT weekday service resumed Monday, ending Midtown Direct diversions to Hoboken and cross-honoring arrangements between Newark and Secaucus.
Unlike the century-old swing bridge opened in 1910, which frequently stuck open or failed to lock properly after rotating for maritime vessels, the new Portal North Bridge is a fixed-span structure rising 50 feet above the Hackensack River. The doubled vertical clearance allows marine traffic to pass underneath uninterrupted without halting commuter and intercity trains.
“New Jersey commuters deserve to get to work on time and get home to their families without a century-old bridge holding up the entire Northeast Corridor,” Sherrill said in a statement. “With both tracks of the Portal North Bridge now in service, we are eliminating a major source of delays and delivering the reliable transportation our residents and economy depend on.”
The transition from the legacy structure to the new two-track bridge occurred in two major phases during 2026:
- First Track Cutover: Conducted between Feb. 13 and March 15, shifting initial rail traffic onto the new span while the legacy swing bridge remained partially active.
- Second Track Cutover: Executed from Oct. 9 through Nov. 16, transferring remaining rail operations onto the new bridge and permanently taking the 1910 swing bridge out of service ahead of its scheduled demolition in 2027.
Constructed under a $1.56 billion contract awarded in October 2021 to Skanska/Traylor Bros PNB Joint Venture—the largest single construction award in NJ TRANSIT’s history—the project spans 2.44 miles of the Northeast Corridor. Major infrastructure elements included 45 million pounds (23,000 tons) of structural steel, 219,000 cubic yards of concrete, more than 35 miles of pipe piles, and 4,850 linear feet of retaining walls.
Funding for the bridge combined investments from the U.S. Department of Transportation, New Jersey, New York, and Amtrak, including $926 million through the Federal Transit Administration and $771 million administered via the Federal Railroad Administration.
“Today, our customers begin benefiting from a generational investment that will make their trips more reliable for decades to come,” NJ TRANSIT President and CEO Kris Kolluri said in a statement. “The new Portal North Bridge permanently removes a chronic source of delays, allowing marine traffic to pass beneath the bridge without interrupting the trains carrying our customers to work, home and everywhere in between.”
Amtrak Interim President Byl Herrmann noted that the completed cutover immediately improves reliability for both commuter and intercity riders. “Thanks to the hard work of our crews, and our strong partnership with NJ TRANSIT, both of our customers can now experience the full benefits of the bridge with more reliable, faster service,” he said.
Gateway Development Commission CEO Tom Prendergast called the opening a pivotal step toward doubling rail capacity between Newark and New York alongside the ongoing Hudson Tunnel Project. “Today’s achievement sends a clear message: the fast, reliable commute that hundreds of thousands of daily riders have long awaited is on the horizon,” Prendergast said.
Members of New Jersey’s congressional delegation—including Sens. Cory Booker and Andy Kim and Reps. Frank Pallone, Josh Gottheimer, Rob Menendez, Nellie Pou, LaMonica McIver, Herb Conaway Jr., and Analilia Mejia—joined state legislative leaders and union officials from the Hudson County Building & Construction Trades Council in hailing the bridge’s completion as a long-awaited fix for one of the region’s most persistent transit bottlenecks.